Redefining the impact of project delays on cost

7/4/2017

0 Comments

 
Project delays can have a significant impact on trust and budget if not handled adeptly from the start, and now there are tools which can help to transform the challenge
by
Dr Hendrik Prinsloo,
Course Facilitator, The Association of South African Quantity Surveyors (ASAQS)
​
Picture
When it comes to delays and the assessment of delay claims, there is limited guidance available. In fact, there is no clear path in terms of managing the issue, establishing process or determining who is ultimately responsible. The result is that many unexpected delays end in disputes which can potentially impact on relationships and the success of a project. There has long been a need for the industry to have access to a simple, standardised process which walks all parties through the claim and finds equally simple answers to the problems.

This need inspired the development of the Decision Support Framework, a tool designed to assist in the assessment of claims from the start, eliminating indecision and uncertainty and providing users with a clear route to resolution. The framework was crafted over a number of years, and was designed to be easy to understand and capable of managing claims across industry and incident. The Decision Support Framework is currently being integrated as part of the Association of South African Quantity Surveyors’ (ASAQS) member toolkit via continuous professional development (CPD) training courses which are being offered around the country. The intended outcome is to assist quantity surveyors in making accurate assessments, determining root causes and, ultimately, saving customers money. 

Alongside supporting the more accurate and efficient assessment of delay claims, the tool adds a sense of fair play – the standardisation of process and procedure allowing all parties equal say. Often, there is no small measure of uncertainty when it comes to claim assessments, so if all parties are using the same resource, it ensures that both client and contractor have the same input, see the same results and have their concerns acknowledged. This can also have a positive impact on time spent with claims, reducing disputes and saving on costs.

The goal is to complete the project, not become embroiled in lengthy debate or lose money as the days tick by and the build remains dormant.  

In any industry, time is money. More so in the construction industry where time delayed decisions can result in a cost per day impact. Likewise, a delay in the delivery of materials to site, can impact costs. By identifying delays and ensuring swift resolution, the Decision Support Framework can have immediate and long-term cost savings. The quantity surveyor can assist in determining the delay far more efficiently and this can significantly lower the financial implications which normally come hand in hand with any delay claim. 

The Decision Support Framework sidesteps the usual problems by taking the user through four primary decision making processes. Each of these has been carefully researched to fit alongside the extension of time claims, and each one uses a process to allow for deliberation and careful resolution. The tool helps to arrive at the easiest conclusion as users follow the steps to a solution and find a mutually beneficial agreement.

For those who are cost conscious and who always keep a keen eye on the bottom line, this Decision Support Framework methodology will add another metaphorical arrow to the professional quantity surveyors quiver. By virtue of the work that quantity surveying professionals undertake, they regularly find themselves at the centre of cost related misunderstandings, while being ever mindful of bringing the project home within budget. 

The ASAQS’s EduTech Division has identified the need to bring clarity to both the construction industry and to the associations QS professionals, by offering bespoke training that provides the participant with a broad understanding of the principles and best practice around this sensitive issue. 

ENDS

MEDIA CONTACT: Cathlen Fourie, 082 222 9198, [email protected], www.atthatpoint.co.za  
 
For more information on ASAQS please visit:
Website: http://www.asaqs.co.za/
Facebook: The Association of South African Quantity Surveyors

0 Comments



Leave a Reply.

    Welcome to the ASAQS Newsroom.

    Archives

    June 2025
    March 2025
    February 2025
    October 2024
    August 2024
    July 2024
    August 2023
    September 2022
    June 2022
    April 2022
    March 2022
    January 2022
    November 2021
    August 2021
    August 2020
    July 2020
    February 2020
    October 2019
    September 2019
    August 2019
    May 2019
    March 2019
    February 2019
    December 2018
    November 2018
    October 2018
    September 2018
    June 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    August 2017
    June 2017
    April 2017
    February 2017
    November 2016
    October 2016

    Categories

    All
    AECOM
    Alternative Building Methods
    Alternative Walling And Roofing
    AS
    ASAQS
    ASAQS Conference
    Association Of South African Quantity Surveyors
    Bert Van Den Heever
    BIM
    BoQ
    Building A House
    Building Costs
    Building Project Delays
    Calculating Building Cost
    Career
    Chris De Wet
    Community Development
    Construction
    Corruption
    Dr Hendrik Prinsloo
    Fraud
    Green Building
    Herman Berry
    Infrastructure Projects
    James Hanley
    Larry Feinberg
    MoU
    Newton Baloyi
    NHBRC
    Pacific Association Of Quantity Surveyors
    Per Square Metre Cost
    Quantity Surveyor
    RICS
    SACAP
    SACPCMP
    Socio-economic Impact
    Value Management

    RSS Feed

CONTACT US

office [at] atthatpoint [dot] co [dot] za
© COPYRIGHT 2025
ALL RIGHTS RESERVED
  • home
  • our story
  • our services
  • your resources
  • SA Industry News